When an agency protest is received by a Contracting Officer, the typical first step is to suspend contract performance. This action is taken to ensure that no further progress is made on the contract while the protest is being evaluated. Suspending performance helps to protect the integrity of the procurement process and allows the agency to thoroughly assess the validity of the protest without any ongoing actions potentially complicating the situation.

This pause in performance is crucial as it allows for a fair and transparent review of the issues raised in the protest, ensuring that all parties involved have the opportunity to present their case. Once the suspension is in place, the Contracting Officer can work on resolving the protest, which may include conducting a detailed evaluation of the claims being made. This step is foundational in maintaining fair competition and adhering to legal obligations within government contracting processes.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy