In the context of government contracting, what is considered unallowable?

Prepare for the Back‑to‑Basics (BtB) Contracting Certification Exam. Benefit from flashcards and multiple choice questions, each with hints and explanations. Ace your certification exam!

In the realm of government contracting, unallowable costs are specifically defined as those costs that are prohibited from being reimbursed under government contracts, typically as a result of laws, regulations, or contract stipulations. When determining unallowable costs, the guidance provided by the Federal Acquisition Regulation (FAR) is crucial, as it outlines specific instances of costs that cannot be charged to government contracts.

Costs excluded by law or regulation refer to expenditures that the government has explicitly stated are not allowable for reimbursement under federal contracts. This can include expenses such as entertainment costs, certain lobbying expenses, and other specified categories that fall outside the allowable cost framework. Understanding this concept is vital for contractors to ensure compliance and avoid financial penalties.

The other options deal with different aspects of cost management or project scope but do not meet the criteria for unallowability as specifically delineated by laws or regulations. For instance, costs that cannot be negotiated may still fall within allowable categories, while unanticipated changes in project scope pertain more to project management and potential adjustments rather than being categorized as unallowable costs. Similarly, costs that are higher than the market rate may be a consideration in price negotiations and may raise concerns about reasonableness but do not inherently make the costs unallow

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy