What qualifies as an excusable delay for contractors?

Prepare for the Back‑to‑Basics (BtB) Contracting Certification Exam. Benefit from flashcards and multiple choice questions, each with hints and explanations. Ace your certification exam!

An excusable delay for contractors refers to situations in which the contractor is not held liable for delays that are beyond their control. The correct answer, which identifies acts of the Government or natural disasters, falls into this category because these are external circumstances that can significantly impact a contractor’s ability to complete their work as scheduled.

Government actions, such as changes to regulations, permitting delays, or other administrative issues, are instances where the contractor cannot be faulted for delays arising from interactions with governmental entities. Similarly, natural disasters like hurricanes, earthquakes, or floods can make it impossible for contractors to carry out their work safely and effectively, therefore constituting a valid reason for a delay that is excusable.

Other options like loss of key personnel, supplier delays, and equipment failure generally do not qualify as excusable delays. Loss of key personnel is often seen as a management issue, and contractors are expected to have contingency plans for such events. Supplier delays can arise from inadequate planning or contract terms that need to be enforced, which puts the onus on the contractor to manage their supply chain effectively. Equipment failure may indicate poor maintenance or selection of suitable machinery, which is typically considered the contractor's responsibility. In contrast, delays caused by government actions or natural events fall into

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy